Question asked by andreassauer on Apr 3, 2019
Latest reply on Apr 8, 2019 by andreassauer

Hello,

I have a chart where I show actuals per week (primary axis) and cumulated values (secondary axis) of milestone progress. The cumulated values are YMT with a cycle of 999.

 

 

As you can see in the graph the cumulated values are in week 02-2019 about 1,200. Is it possible to start the cumulation of the values in the selected time range and not before? So that in week 02-2019 the cumulated is the same as actual.

 

I cannot use YCV because we often analyze over several years and it should not start at 0 each year. In my example I would need a function that starts to cumulate the values at the begin of the selected time range and stop at the end of the selected time range.

 

Thanks in advance.