I'm encountering a critical issue following my functional test. I can't find the correct Variance amount on the Sales Planning screen.
I also noticed that several people have encountered this problem but without a validated solution.
I've performed all possible checks:
SET- PLN-Initialize Planning
SET - Flag Planning and Actual Years
SET - Lock Planning
SET - Unlock Planning
- Database security
Screen: Administration
After checking, I think there's an issue with the forecast calculation procedure, as shown in the screenshot below: I can correctly identify the 3 months of actual figures, but there's a gap in the remaining 9 months of the budget to complete the forecast:
If you have solved this problem or have any ideas on how to solve it, I would be very grateful so that I can continue my training.
Thanks