Level 300 part 1: module 303

Hi Team,

I mistakenly added the 12 actual months on the FCST9+3 and now I cannot see the variance for the functional test. Can you help out?

thanks

Accepted Answer

  • John Williams
    John Williams Employee
    10 Comments Level 300: Expanding Board in Your Organization Name Dropper Board Developer
    Answer ✓

    Carlos Ballester

    Thank you for the screenshots you have shared with us.
    I would request you to put "EDIT/VIEW" (including the " " ) into the Column Algorithm section. As shown in the below screenshot:

    Could you kindly confirm if you are able to make changes to the "Planning Months" section and update the Planning version as expected? I believe this should resolve the issue for you. For your convenience, I've included a recording with step-by-step instructions below. (Copy and paste the URL in a different tab if the link is not accessible)

    https://nialsmith-gmail.tinytake.com/msc/MTA1ODkxNTBfMjQyOTI1OTU

Answers

  • @Carlos Ballester

    Thank you for bringing this to our attention.

    Could you please confirm if you navigated to the "Administration" screen, entered Design mode, and followed the steps to configure the layout by selecting "Configure" on the data block "e" under the "Data View Settings," then went to the "Screen" tab and selected the "Planning Months Settings" screen with the "Same tab" option?

    Could you please provide a screenshot of the layout of the "Planning Month Settings" screen? Additionally, could you share a screenshot of the layout of the Data View that you have shared with us?

    This will help us verify if there are any discrepancies.

  • Hi John

    I think these are the screenshots that you are wanting right?

    I can confirm that everything that you put before I had already done

    thanks

  • Brilliant thanks